PNGRB’s own August 2026 pipeline report puts India’s gas grid at 28,157 km operating and 7,033 km of common-carrier line still to build. The North-East grid is the one big active build; four authorised lines have laid no pipe at all; and the pipelines PNGRB bid out ran at 5% of capacity. Gazette land notices show where the next pipe is going.

Energy Infrastructure · Gas Pipelines · 23 October 2026

India Has 28,000 km of Gas Pipeline Working and 7,000 km Still to Build. A Map of Where, and of the Lines Still on Paper

Skip to article content
Text Size
28,157 of 34,978 kmNatural gas pipeline operating, against length authorised, June 2026 (PNGRB)
7,033 kmCommon-carrier pipeline authorised but not yet operating, across 15 lines
5% vs 32%Capacity used in August 2026 by the pipelines PNGRB bid out, against the whole common-carrier network
1,629 kmOn 4 authorised lines with no pipe yet lowered, including one authorised in 2014

India’s natural gas grid is mostly built, slowly being finished, and barely being added to. PNGRB’s own monthly pipeline report for August 2026 puts 28,157 km in operation out of 34,978 km authorised, as of June 2026. Its common-carrier lines have 7,033 km still to build, spread over 15 pipelines; almost all of that length belongs to lines authorised between 2011 and 2020, and 4 of them, with 1,629 km between them, have not lowered a single kilometre of pipe. Only one new gas trunk line has been authorised since 2023, and two others bid out in 2023–24 have no award.

The map below shows where the work is. It combines the regulator’s line-by-line status, the lines PNGRB has authorised or bid out but nobody has started, the routes its 2025 expert committee proposes for 2040, and the Gazette notices by which the petroleum ministry acquires the right to lay pipe under private land.

Updated 28 October 2026. The right-of-user notices in the table below were checked against the Gazette of India’s own text, via the SansadSaar index of the archive.org Gazette of India collection. Two S.O. numbers were wrong and are corrected: the 31 July 2025 section 3(1) notice for Silchar–Panisagar in Assam is S.O. 3577(E), not 3574(E) (S.O. 3574(E) of the same date is the Panisagar–Aizawl section in Mizoram), and the 14 January 2026 section 6(1) declaration for Visakh–Raipur in Odisha is S.O. 221(E), not 5079(E). Seven more rows now carry Gazette numbers, and Srikakulam–Angul (5703(E)), the Silchar city-gas spur (3223(E)), Mundra–Pachpadra (2247(E)) and Dahej–Parvat (1303(E)) match. S.O. 5085(E), 2993(E) and 3755(E) could not be found in the index, which does not hold every Gazette issue, so they stay as reported.
Updated 23 October 2026. Revised on the day of publication with PNGRB’s own monthly reports for August 2026 on natural gas pipelines and city gas distribution. Line status, lengths and target dates now come from the regulator’s table rather than press reports; operating length is 28,157 km of 34,978 km authorised (June 2026), not 27,427 of 34,273 (December 2025); new sections cover how much capacity each group of pipelines used in August 2026 and the city gas networks’ pipe-laying; Mumbai–Nagpur–Jharsuguda is now shown as operating. The headline and title changed accordingly.

The map

Barmer–Jaisalmer–Jodhpur–Bikaner–Churu (unassigned) Kakinada–Vijayawada–Kadapa–Chittoor (unassigned) Digha–Kolkata–Paschim Medinipur (alternate) (unassigned) Mangalore–Shimoga–Dharwad (alternate) (unassigned) Jabalpur–Shahdol (unassigned) Rewa–Chhatarpur–Jhansi (unassigned) Lucknow–Begusarai (unassigned) Ramagundam–Nagpur (unassigned) Narsinghpur–Amliha–Godhi (unassigned) Purnia–Ranaghat (unassigned) Raipur–Koraput (unassigned) Ramgarh–Barmer (unassigned) Bengaluru–Arkula (unassigned) Salem–Madurai (unassigned) Rajgarh–Bhopal–Aurangabad (unassigned) Nargund–Vijayapura–Barshi (unassigned) Barshi–Beed–Vadap (unassigned) Shillong–Gambegre (unassigned) Gadag–Ballari (unassigned) Golaghat–Itanagar (unassigned) Hyderabad–Kurnool (unassigned) Jorhat–Kohima (unassigned) Kolaghat–Jajpur (unassigned) HVJ trunk: Hazira–Vijaipur–Jagdishpur (GAIL) Dahej–Vijaipur (DVPL / DVPL-II) (GAIL) Vijaipur–Dadri (GREP / VDPL) (GAIL) Dahej–Uran–Panvel–Dabhol (DUPL/DPPL) (GAIL) Kochi–Koottanad–Mangaluru (KKBMPL phase I/II-Mangaluru) (GAIL) East–West Pipeline (Kakinada–Hyderabad–Bharuch) (PIL (Pipeline Infrastructure Ltd)) KG Basin network (summary) (GAIL) Cauvery Basin regional (summary) (GAIL) Dadri–Bawana–Nangal (DBNPL) (GAIL) Chhainsa–Jhajjar–Hisar (CJHPL) (GAIL) Dadri–Panipat (IOCL) GSPL Gujarat high-pressure grid (summary spine) (GSPL) Shahdol–Phulpur (SPPL) (RGPL (Reliance Gas Pipelines)) AGCL Assam regional network (AGCL) JHBDPL: Jagdishpur–Phulpur–Varanasi–Dobhi–Patna–Barauni (GAIL) JHBDPL: Dobhi–Bokaro–Durgapur (GAIL) JHBDPL: Bokaro–Angul–Dhamra (+Paradip) (GAIL) JHBDPL: Durgapur–Kolkata–Haldia (GAIL) Barauni–Guwahati (BGPL, part of JHBDPL) (GAIL) MNJPL: Mumbai–Nagpur (GAIL) MNJPL: Nagpur–Jharsuguda, Maharashtra section (GAIL) MNJPL: Nagpur–Jharsuguda, Chhattisgarh–Odisha section (GAIL) Mallavaram–Bhopal–Bhilwara–Vijaipur: operating section (Kunchanapalli–Ramagundam) (GITL (GSPL India Transco)) Ennore–Puducherry–Nagapattinam–Tuticorin (ETBPNMTPL coastal trunk) (IOCL) NE Gas Grid: Guwahati–Numaligarh (IGGL (Indradhanush Gas Grid)) NE Gas Grid: Phase I north-bank / Arunachal link (IGGL (Indradhanush Gas Grid)) Jammu–Srinagar (bid Jan 2024) (unassigned) Ennore–Barshi (bid Dec 2023) (—) Kakinada–Vijayawada–Nellore (IMC Ltd) Ennore–Nellore (GTIL) Kanai Chhata–Panitar (HPPL (H-Energy consortium)) Kakinada–Srikakulam (APGDC (not named in HLEC)) Jaigarh–Mangalore (H-Energy (not named in HLEC)) Kochi–Kanyakumari–Thoothukkudi (IOCL) Anjar–Palanpur spur (approved Mar 2025) (GSPL) Dabhol–Bengaluru (DBPL) (GAIL) JHBDPL: Dhamra–Haldia (GAIL) Srikakulam–Angul (SAPL) (GAIL) Mehsana–Bhatinda (MBPL) (GIGL (GSPL India Gasnet)) Bhatinda–Gurdaspur (GIGL (GSPL India Gasnet)) Koottanad–Walayar–Coimbatore–Bengaluru (KKBMPL Bengaluru leg) (GAIL) Nagpur–Jabalpur (GAIL) Gurdaspur–Jammu (GAIL) Mallavaram–Bhopal–Bhilwara–Vijaipur: unbuilt remainder (GITL (GSPL India Transco)) ETBPNMTPL: Thiruvallur–Bengaluru and Madurai branches (IOCL) Hazaribagh–Ranchi (IOCL) Jamnagar–Dwarka (GSPL) NE Gas Grid: Guwahati–Shillong–Silchar–Agartala (hill sections) (IGGL (Indradhanush Gas Grid)) NE Gas Grid: Dimapur–Kohima–Imphal (IGGL (Indradhanush Gas Grid)) Srikakulam–Angul (GAIL), Odisha JHBDPL spur (GAIL), Howrah/Hooghly MNJPL Nagpur–Jabalpur (GAIL), Chhindwara MNJPL (GAIL), Bhandara MNJPL (GAIL), Chhattisgarh NE grid (IGGL), Golaghat NE grid Dergaon–Dimapur (IGGL) NE grid Silchar–Panisagar (IGGL) NE grid Panisagar–Aizawl (IGGL), Mizoram/Tripura HRRL refinery spur (Mehsana–Bhatinda), Rajasthan Dahej–Parvat ethane (Reliance), Gujarat Visakh–Raipur products (HPCL), Odisha/AP Mundra–Pachpadra crude (HPCL/HRRL) Mundra–Panipat crude (IOCL), Haryana Paradip–Numaligarh crude (NRL), Assam Irugur–Devangonthi products (BPCL) Jalandhar–Goindwal LPG (IOCL), Punjab Kandla–Gorakhpur LPG (IHB), Anand Haldia–Panagarh LPG (HPCL), West Bengal Delhi Mumbai Kolkata Chennai Bengaluru Hyderabad Nagpur Guwahati Dahej LNG terminal Hazira LNG terminal Mundra LNG terminal Chhara LNG terminal Dabhol LNG terminal Kochi LNG terminal Ennore LNG terminal Dhamra LNG terminal Operating Being built / part operating Authorised, not started Bid out, no award yet Proposed (PNGRB committee, 2025) LNG terminal Right-of-user notice 2025–26, gas line same, crude/product/LPG Routes schematic, through named towns; markers at district level. Outline: datameet India composite. Status: PNGRB, PPAC, company and press reports.

Orange lines are where pipe is being laid: the North-East grid, the Mehsana–Bhatinda line across Rajasthan to Punjab and on to Jammu, the unfinished parts of the Kochi–Bengaluru and Ennore–Bengaluru lines in the south, Srikakulam–Angul on the east coast, the last stretches of the Jagdishpur–Haldia–Bokaro–Dhamra line, and the long-stalled Mallavaram–Bhilwara line through the centre. Red dashes are authorised lines with no pipe laid. The purple markers are pipelines that had right-of-user notices published in the Gazette in 2025–26; filled markers are gas lines.

How much is built

Natural gas pipelinesAuthorised, kmOperating, kmUnder construction, kmAs onSource
All lines incl. tie-ins and dedicated lines34,97828,157–June 2026PNGRB MIS report, August 2026
Common-carrier lines33,20226,6467,033June 2026PNGRB MIS report, August 2026 (entity chart)
of which GAIL19,05818,3541,273June 2026same
All lines incl. tie-ins (earlier figure)34,27327,4278,48931 Dec 2025PPAC Ready Reckoner, May 2026, Table 20

PNGRB, “PNGRB MIS Report: NGPL – Natural Gas Pipelines, Month of August 2026” (Statistics Division; data submitted by entities; length data quarterly, as on June 2026). The common-carrier and GAIL rows are summed from its entity chart; the under-construction total equals the sum of the line-by-line table below. PPAC’s December 2025 figures are shown for comparison; its under-construction figure includes tie-in and dedicated lines.

GAIL owns 18,354 km of the 26,646 km of operating common-carrier pipeline, about 69%. Operating length rose by about 730 km between PPAC’s December 2025 figure and PNGRB’s June 2026 one. GAIL’s Mumbai–Nagpur–Jharsuguda line is now listed as operating, with 1,707 of its 1,755 km built.

Where pipe is being laid, line by line

LineEntityAuthorised, kmOperatingUnder constructionPipe loweredHydrotestedTarget date as printedCapacity used, Aug 2026
North-East Natural Gas Pipeline GridIGGL1,8633921,4711,139795Mar-264%
Mallavaram–Bhopal–Bhilwara–VijaipurGITL1,8813651,51600Mar-202%
Mehsana–BhatindaGIGL1,9431,33960460Jun-267%
Kochi–Koottanad–Bangalore–MangaloreGAIL1,104675429288221Mar-2623%
Ennore–TuticorinIOCL1,4311,121310––Mar-257%
Dabhol–BangaloreGAIL1,4141,18223200Feb-1325%
Jagdishpur–Haldia–Bokaro–Dhamra–Paradip–Barauni–GuwahatiGAIL3,5463,315231252128Mar-2654%
Srikakulam–AngulGAIL690470221265221Jun-260%
Bhatinda–GurdaspurGIGL2611011601511Dec-240.3%
Gurdaspur–JammuGAIL160016015278Jul-26–
Hazaribagh–RanchiIOCL7107180Feb-26–
Kochi–Kanyakumari–ThoothukudiIOCL425042500Mar-29–
Kakinada–Vijayawada–NelloreIMC667066700Mar-24–
Kanai Chhata–PanitarHPPL317031700Mar-24–
Ennore–NelloreGTIL220022000Apr-20–

PNGRB MIS report, NGPL, August 2026, page 2 (partially commissioned and under-construction common-carrier pipelines). “Pipe lowered” and “hydrotested” are construction progress on the unbuilt part as reported by each entity; Ennore–Tuticorin’s figures (1,282 km lowered against 310 km under construction) appear to be cumulative, so they are not shown. Target dates are as printed: several have passed, one (Dabhol–Bangalore, February 2013) by thirteen years.

The regulator’s table separates real work from paper. On the North-East grid, 1,139 km of pipe has been lowered and 795 km hydrotested beyond the 392 km in operation — the largest active build in the country. GAIL is finishing the Kochi line to Bengaluru (288 km lowered of 429), Srikakulam–Angul and the Jagdishpur–Dhamra tails, and has lowered 152 of the 160 km of Gurdaspur–Jammu. Mehsana–Bhatinda has 604 km left but only 6 km lowered. Mallavaram–Bhopal–Bhilwara–Vijaipur, due in March 2020, has 1,516 km unbuilt and none lowered.

Four authorised lines show no pipe lowered at all: Kakinada–Vijayawada–Nellore (authorised 2018), Kanai Chhata–Panitar (2019), Ennore–Nellore (2014; its authorisation was reported cancelled in 2019, yet it is still listed), and the newly authorised Kochi–Kanyakumari–Thoothukudi (March 2026, due March 2029). Hazaribagh–Ranchi has 8 km lowered of 71 against a February 2026 target. PNGRB’s 2025 committee proposed alternate routes for the first two, and for Jaigarh–Mangalore, which no longer appears in the report.

Built, but carrying little gas

PipelinesNumberOperating, kmCapacity, MMSCMDGas carried, MMSCMDCapacity used
Bid out by PNGRB (regulation 5)75,406315155%
Authorised by the government before PNGRB (regulation 17; mostly GAIL)1717,97038819250%
Built before PNGRB without central authorisation (regulation 18; GSPL, GGL)32,878534075%
Policy directive (section 42; North-East grid)1392604%
All common-carrier pipelines2826,64676224732%

PNGRB MIS report, NGPL, August 2026, page 4 (monthly figures). Regulation numbers refer to PNGRB’s authorisation regulations.

The pipelines PNGRB has awarded by competitive bidding since 2008 carried 15 MMSCMD in August 2026 against 315 MMSCMD of capacity, about 5%. The older GAIL lines authorised before the regulator existed ran at 50%, and GSPL’s Gujarat grid at 75%. Line by line, Dahej–Uran–Panvel–Dabhol ran at 124% of its capacity, GSPL’s high-pressure Gujarat grid at 89% and the HVJ trunk at 70%; Mehsana–Bhatinda and Ennore–Tuticorin at 7%, Mumbai–Nagpur–Jharsuguda and the North-East grid at 4%, and Srikakulam–Angul at 0%. The newest lines were built to reach markets that do not yet take much gas, which is the same pattern this blog found in LNG terminals.

City gas: the other pipe being laid

Most of the pipe going into the ground in India is not trunk line but city gas distribution. PNGRB’s city gas report for August 2026 shows its authorised networks with 3,30,815 inch-km of steel pipeline laid against a pro-rata target of 4,10,808 inch-km (81%) and a full work-programme target of 5,47,158 inch-km. They have built 9,115 CNG stations against a pro-rata target of 7,698, but connected 1.75 crore homes to piped gas against a pro-rata target of 4.62 crore (38%). The newest areas, authorised in 2024 across the North-East, Sikkim and Jammu and Kashmir, report almost nothing built yet, which matches the North-East trunk grid still being under construction.

What the Gazette shows: land being acquired now

Before a pipeline can be laid across private land, the petroleum ministry publishes a notice under section 3(1) of the 1962 Right of User Act naming the villages and survey numbers on the route, then a section 6(1) declaration once objections are settled. This piece found notices from 2025–26 for at least five gas projects (counting the North-East grid’s sections once) and nine crude, product, ethane or LPG lines.

PipelineEntityCarriesWhereLatest stepS.O. (checked against the Gazette, 28 Oct 2026)
Srikakulam–Angul and spurGAILGasOdisha (Rayagada, Koraput, Gajapati, Ganjam)s.3(1) 4 Dec 2025; s.6(1) 20265703(E)
Jagdishpur–Haldia–Bokaro–Dhamra spurGAILGasWest Bengal (Howrah, Hooghly)s.3(1) 16 Dec 2025; s.6(1) 4 May 20265834(E); 2240(E)
Mumbai–Nagpur–Jharsuguda, incl. Nagpur–JabalpurGAILGasMaharashtra, Madhya Pradesh, Chhattisgarhs.6(1) 2025 (MP); s.3(1) Dec 2025 (Chhattisgarh)3755(E) (2024 s.3(1), as reported); 5855(E) (s.6(1), 16 Dec 2025, MP)
North-East Gas Grid: Silchar–PanisagarIGGLGasAssams.3(1) 31 Jul 2025; s.6(1) Dec 20253577(E) (corrected from 3574(E))
North-East Gas Grid: Panisagar–AizawlIGGLGasMizoram, Tripuras.6(1) Nov 2025 (Mizoram); s.3(1) 11 Jun 2026 (Tripura)5085(E); 2993(E) (as reported; not found in the Gazette index); s.3(1) Mizoram 31 Jul 2025: 3574(E)
North-East Gas Grid: Guwahati–Numaligarh–Dimapur, Dergaon–DimapurIGGLGasAssam (Golaghat)s.3(1) Mar and Jun 20263229(E); 3279(E) (June)
North-East Gas Grid: Silchar city-gas spurIGGLGasAssam (Cachar)s.3(1) 18 Jun 20263223(E)
Mehsana–Bhatinda: spur to HPCL Rajasthan RefineryGIGLGasRajasthan (Jalore–Balotra)s.3(1) 25 Nov 2025; s.6(1) Dec 20255448(E) (s.3(1))
Mundra–Panipat (new crude line)IOCLCrudeHaryanas.3(1) 8 Dec 2025—
Mundra–PachpadraHPCL / HRRLCrudeGujarat, Rajasthans.6(1) 5 May 20262247(E)
Paradip–NumaligarhNRLCrudeAssams.3(1) Jul 2025; s.6(1) later—
Visakh–RaipurHPCLProductsAndhra Pradesh, Odisha, Chhattisgarhs.6(1) 14 Jan 2026 (Odisha)221(E) (corrected from 5079(E))
Irugur–DevangonthiBPCLProductsTamil Nadu, Karnatakas.6(1) 15 Dec 20255826(E)
Dahej–ParvatRelianceEthaneGujarats.6(1) 11 Mar 20261303(E)
Kandla–Gorakhpur (Gujarat section)IHBLPGGujarat (Anand)s.6(1) Dec 2025—
Haldia–PanagarhHPCLLPGWest Bengals.3(1) Apr and Aug 20261832(E)–1834(E); 4588(E)–4590(E)
Jalandhar–Goindwal SahibIOCLLPGPunjab (Kapurthala)s.6(1) 17 Dec 2025—

Notices under the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962: section 3(1) announces the intention to acquire the right of user along a route and invites objections; section 6(1) declares it acquired. Every entry was first found through search-result summaries of the Gazette or of legal-notice sites; on 28 October 2026 the S.O. numbers were checked against the Gazette’s own text through the SansadSaar index of the archive.org Gazette of India collection, and two were corrected. Three numbers that index does not hold are marked as reported. About a dozen ONGC field and gathering-line notices are left out. Two reported numbers that do not fit the Gazette’s own numbering sequence have been dropped.

The North-East grid has the most fresh gas notices, consistent with PNGRB’s figures showing it as the largest active build. Some notices are not new work: parts of Mumbai–Nagpur–Jharsuguda had been reported mechanically complete before notices for those stretches appeared. No 2025–26 notice was found for Kochi–Kanyakumari–Thoothukudi, Mallavaram–Bhilwara or the stalled Andhra Pradesh and West Bengal lines; absence from search results is not proof that none exists.

Bids and approvals: few new lines

The only new gas trunk line authorised since 2023 is IOCL’s 425 km Kochi–Kanyakumari–Thoothukudi line, dated 9 March 2026 in PNGRB’s report, which would connect Petronet’s under-used Kochi LNG terminal to IOCL’s Ennore–Tuticorin system; IOCL’s board approved ₹2,448.70 crore for it on 21 September 2026. PNGRB’s 2026 bidding round has been for LPG pipelines. From 1 January 2026 PNGRB also cut the unified gas transport tariff from three zones to two, about ₹54/MMBtu up to 300 km and ₹102.86 beyond, with city gas paying the first rate everywhere.

LineEntitykmStatus
Ennore–Barshibid, no award~875Bids invited December 2023, due May 2024; no award found; not in PNGRB’s August 2026 report
Jammu–Srinagarbid, no award~325Bids invited January 2024, due May 2024; no award found; not in the report
Anjar–Palanpur spurGSPL274Approved by PNGRB in March 2025 as part of GSPL’s grid, capex ₹2,051.18 crore
Jaigarh–MangaloreH-Energy635Authorised 2016; reported cancelled July 2022; absent from PNGRB’s August 2026 report, though its 2025 committee still listed it

PNGRB bid notices and approvals as reported in the trade press; Global Energy Monitor for the Jaigarh–Mangalore cancellation.

The PNGRB committee’s 2040 plan lists 25 further routes totalling about 9,600 km — the blue dotted lines on the map, one of which (Kochi–Kanyakumari) has since been authorised.

What doesn’t follow from any of this

The map is schematic: each line is drawn through the towns its route names, not along its surveyed alignment, and the Gazette markers sit at district level. Line status and utilisation come from PNGRB’s August 2026 reports, which rest on data the pipeline companies submit; target dates are printed as the companies last gave them and many have passed. Lowered and hydrotested lengths may be defined differently by different companies. The Gazette entries were found through search summaries and then checked against the Gazette’s own text where the SansadSaar index holds the notice; three were not found there. A right-of-user notice shows land being acquired, not pipe being laid.

What would fix this

  • PNGRB should publish its monthly pipeline report as a machine-readable table, with every past target date for each line beside the current one, so that a target of February 2013 still printed in 2026 is visible as thirteen years of slippage.
  • PNGRB should decide the authorisations with no pipe laid — Kakinada–Vijayawada–Nellore, Kanai Chhata–Panitar and Ennore–Nellore — by cancelling or re-bidding them, so its committee’s alternate routes can be offered.
  • PNGRB should require bid-out pipelines to report contracted and used capacity separately, so the 5% utilisation of competitively bid lines can be traced to missing demand, missing connections or missing contracts.
  • The petroleum ministry should publish an index of its Right of User Act notices by pipeline, section and date, so that land acquisition can be tracked against construction.
  • PNGRB should report the outcome of the Ennore–Barshi and Jammu–Srinagar bids, which closed in May 2024.

These are proposals from this blog, not recommendations any agency has adopted.

Sources and caveats

PNGRB Statistics Division, “PNGRB MIS Report: NGPL – Natural Gas Pipelines, Month of August 2026” and the city gas distribution MIS report, “Progress of PNG D, CNG and Pipeline (Inch-Km) in the Country – August 2026” (as on 31 August 2026), both supplied to this blog as PDFs and read in full. PPAC, Snapshot of India’s Oil & Gas data (Monthly Ready Reckoner), May 2026, Table 20 (as on 31 December 2025). PNGRB High Level Expert Committee, “Vision 2040 – Natural Gas Infrastructure in India” (10 November 2025): bid-out pipelines, alternate and proposed routes. Bids, approvals and cancellations: PNGRB public notices, GAIL and IOCL stock-exchange disclosures, Global Energy Monitor and trade press (Indian Infrastructure, World Pipelines, Business Today, Tribune, Indian Chemical News and others), read through search-result summaries. Right-of-user notices: Gazette of India notifications under the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962, as summarised by search results and legal-notice sites; S.O. numbers checked on 28 October 2026 against the Gazette’s own text via the SansadSaar index of the archive.org Gazette of India collection (for example CG-DL-E-06082025-265243 for S.O. 3577(E), CG-DL-E-17012026-269419 for S.O. 221(E), CG-DL-E-13122025-268474 for S.O. 5703(E)). Map outline: datameet, India composite boundary. Route geometry is this blog’s schematic. Research notes and the report text: out/research/pipelines/ in this blog’s archive.

About this article: Researched, written and edited by Umashankar Triplicane Dwarakanathan, with AI research assistance; every figure is meant to trace to the primary source cited. See the Editorial Policy for how sourcing, AI use and corrections work.

Umashankar Triplicane Dwarakanathan
Contact Us
Umashankar Triplicane Dwarakanathan
Investment Promotion & Energy-Sector Leader · Chennai, Tamil Nadu, India
LinkedIn → GitHub → Email +91 78273 81696
How this site works

Data-led analysis of India's trade, currency and industrial policy. Every article is built from primary official sources, and every figure links back to the release, table or filing it came from.

Sources. DGCI&S TradeStat (imports/exports, HSN-wise) · PIB (government press releases, January 2017 to today, refreshed daily) · RBI (circulars, balance of payments) · MoSPI (CPI/WPI, IIP) · PARIVESH (environmental clearances) · CCIL (bond yields) · BIS (policy rates) · SEBI, NSE/BSE and SEC filings for company data.

Interpretation. Figures carry their vintage and retrieval date; estimates and press-reported numbers are labelled as such; where sources disagree, both are shown. Corrections are made visibly, never silently. Articles are written with AI assistance from the cited sources — AI-generated text can misstate figures even when working from real material, so verify any number that matters to a decision against the linked primary source.

footer

Browse all articles by topic

Every piece on this blog, grouped. Or read the full index.

Agriculture & FertilisersAI ToolsChemicalsClimate & CarbonEnergy & FuelsGas & LNGImport SubstitutionIndustrial PolicyMarkets & FinanceMobility & EVPrices & InflationTextilesTrade & Tariffs

Each topic is a live archive page that updates itself as pieces are labelled. It replaces a hand-kept list that had fallen 18 articles behind.