The new Rs 84,084 crore offshore scheme shares the cost of 60 deepwater wells and pays for new seismic surveys. Its 600 MMTOE reserve target is about ten years of India’s output; the harder test, on India’s record, is turning finds into production.

Energy · 27 October 2026

Samudra Manthan Pays Up to Rs 675 Crore a Well. India’s Last Deepwater Bets Show Discovery Is the Easy Part

Skip to article content
Text Size
Rs 84,084 crof public money for offshore exploration, surveys and shared infrastructure to 2030-31
Rs 675 crmaximum support per deepwater well, half of a well costing about $142 million
600 MMTOEof new reserves targeted, about 10 years of India’s current oil and gas output
14 → 1OALP discoveries to producing fields since 2017, the record the scheme has to beat

This blog’s piece on India’s exploration licensing found that the Open Acreage Licensing Programme had awarded about 172 blocks and $4.36 billion of committed work since 2017, for 14 discoveries and one marginal producing field. On 31 July 2026 the Cabinet approved a different approach for the hardest acreage. Samudra Manthan, the National Offshore Exploration Scheme, puts Rs 84,084 crore of public money into surveying the seabed, sharing the cost of deepwater wells and building shared offshore infrastructure, up to 2030-31.

This piece sets out what the money buys, what a deepwater well costs, what the reserve target means against India’s output, and what the country’s last deepwater bets suggest about the step after a discovery.

What the money buys

Samudra Manthan, Rs 84,084 crore to 2030-31: where it goes Drilling 60 deepwater wells 43,200 Seismic and other data 28,534 Shared offshore hubs 10,000 Manufacturing and services zones 2,000 Not itemised in reports 350 Rs crore. Components as reported from the Cabinet decision of 31 July 2026.

About half the outlay pays for drilling, a third for data. The seismic share of Rs 28,534 crore splits into Rs 12,000 crore of basin-wide 2D surveys, Rs 12,534 crore of 3D and other geophysics, and Rs 4,000 crore to reprocess data already in the National Data Repository. The four components reported sum to Rs 83,734 crore, Rs 350 crore short of the total; the reports do not say what the rest is for.

The drilling arithmetic has a gap too. The government will pay up to half the eligible cost of each deepwater well, capped at Rs 675 crore (some reports say Rs 650 crore). Sixty wells at the cap is Rs 40,500 crore, but the drilling line is Rs 43,200 crore, or Rs 720 crore a well. The Rs 2,700 crore difference could pay for about 4 more wells at the cap, or may cover drilling costs outside the per-well support; the release as reported does not explain it.

What a deepwater well costs

Cost of one deepwater well, $ million Minister, Sept 2026 (typical deep-sea well) 100 Swarajya, Samudra Manthan areas 120–145 Stratigraphic campaign, first estimate (Rs 800 cr) 84 Stratigraphic campaign, revised (Rs 1,200 cr) 126 Well cost at which the scheme’s cap binds (Rs 1,350 cr) 142 Rupee figures at Rs 94.93 a dollar (23 Oct 2026). This blog’s arithmetic.

The cap binds on any well costing more than Rs 1,350 crore, about $142 million. That is at the top of the range now quoted for Indian deepwater wells. The petroleum minister put a typical deep-sea well at about $100 million in September, with rigs leasing at around $250,000 a day; Swarajya put wells in the scheme’s target areas at $120–145 million; and the cost of each well in the earlier stratigraphic drilling campaign was reported to have risen from Rs 800 crore to about Rs 1,200 crore. At those costs the scheme pays close to half, which is the intention: it turns a $100–145 million bet into a $50–75 million one for the company drilling.

What 600 MMTOE means

The scheme aims to add more than 600 million tonnes of oil equivalent (MMTOE) of reserves. The government puts the hydrocarbon potential of the eastern and western offshore basins at over 5,600 MMTOE, so the target is about 11% of that potential turned into proved reserves. India produced about 28.0 million tonnes of crude and 34.3 billion cubic metres of gas in 2025-26, provisionally, or about 62 MMTOE on the oil-plus-gas convention the Directorate General of Hydrocarbons uses. 600 MMTOE is therefore about 10 years of current domestic output, a meaningful addition but well short of replacing the 88% of crude that India imports.

The step after a discovery

Earlier deepwater effortWhat was expectedWhat happened
ONGC KG-DWN-98/2 (Krishna-Godavari, east coast)$5.07 bn capex (2018); peak 78,000 b/d oil and 15.57 mmscmd gas in 2017 plans, cut to 45,000 b/d and 10 mmscmdFirst oil January 2024, after a 2021 target; crude about 20,000 b/d and gas reported at 1.5–3 mmscmd in late 2025 and 2026, with geology blamed
Reliance–BP KG-D6 (east coast)Once described as India’s largest gas discovery; D1 and D3 fields producing from April 2009Output fell steeply within a few years of starting; newer R-Cluster (2020), Satellite (2021) and MJ fields (peak about 12 mmscmd) restored part of it
OALP exploration blocks (since 2017)172 blocks awarded, $4.36 bn of committed work14 discoveries reported and 1 marginal field producing
Andaman ultra-deepwater (2025–26)Four exploratory wells in 2025-26; a stratigraphic well spudded 27 January 2026No commercial discovery announced; the minister has cited 46 earlier dry wells in the region

India’s deepwater record is not short of discoveries. KG-D6 and ONGC’s neighbouring KG-DWN-98/2 were both large finds. The trouble came after: complex reservoirs that produced well below plan, development that ran years late, and output that peaked early. ONGC’s block, approved at $5.07 billion of capital spending in 2018, began producing oil in January 2024 instead of 2021, and was reported in 2026 to be producing well under half of its cut-down oil target. The OALP record points the same way: 14 discoveries, one producing field.

Samudra Manthan addresses the first step well. Better seismic data and shared drilling costs should mean more and cheaper wells, and the common hubs could make small finds worth developing. But the scheme’s published targets are counted in wells drilled and reserves added. Neither guarantees production, and the deepwater-and-ultra-deepwater part of OALP Round X, the acreage the scheme is meant to help, had its bid deadline extended for a sixth time, to 15 November 2026.

What would fix this

  • The Ministry of Petroleum and Natural Gas should publish the full component-wise outlay, including the unitemised Rs 350 crore and how the drilling line relates to the per-well cap.
  • Each supported well should be reported on completion with its cost, the support paid and the result, so the cost-sharing can be judged well by well.
  • The scheme should add a production milestone, such as discoveries reaching a development plan within a set number of years, alongside its targets for wells drilled and reserves added.
  • DGH should publish the time from discovery to first production for every offshore discovery since 2000, so delays like KG-DWN-98/2’s can be compared.

These are proposals from this blog, not recommendations any agency has adopted.

What this piece could not establish

The Cabinet release and the PIB background note could not be opened directly; figures come from their text as indexed by search engines and from news reports, which disagree on the per-well cap (Rs 675 crore or Rs 650 crore) and in one case describe about 150 wells rather than 60. The current output of KG-DWN-98/2 differs between reports, and no audited cost overrun was found. KG-D6’s production history is described qualitatively because no consistent annual series was found. Converting gas to oil equivalent at one billion cubic metres per MMTOE follows DGH’s convention and is approximate. Dollar figures use one exchange rate and ignore cost escalation to 2031.

Sources and caveats

Samudra Manthan: Cabinet decision of 31 July 2026 as reported by Outlook Business, Deccan Herald, Deccan Chronicle, Free Press Journal, Angel One and Offshore Technology; component details per Drishti IAS, NEXT IAS and Vision IAS summaries, the PIB background document as indexed, and First Break (seismic split). Well costs: the petroleum minister via Republic World (29 September 2026); Swarajya; the stratigraphic campaign via Chem In Digest. Andaman wells: Drilling Contractor and PSU Watch (2026). KG-DWN-98/2: Business Standard (13 November 2025) and 2026 press reports; 2018 cost estimate per Business Standard. KG-D6: Business Standard (2019), Offshore Technology and Indian Infrastructure (MJ field). Domestic production 2025-26: Ministry of Petroleum and Natural Gas reply to Parliament via The Print. OALP figures and Round X dates: this blog’s OALP piece and its 27 September 2026 update. Per-well arithmetic, dollar conversions and the years-of-output comparison are this blog’s. Nothing here is investment advice.

About this article: Researched, written and edited by Umashankar Triplicane Dwarakanathan, with AI research assistance; every figure is meant to trace to the primary source cited. See the Editorial Policy for how sourcing, AI use and corrections work.

Umashankar Triplicane Dwarakanathan
Contact Us
Umashankar Triplicane Dwarakanathan
Investment Promotion & Energy-Sector Leader · Chennai, Tamil Nadu, India
LinkedIn → GitHub → Email +91 78273 81696
How this site works

Data-led analysis of India's trade, currency and industrial policy. Every article is built from primary official sources, and every figure links back to the release, table or filing it came from.

Sources. DGCI&S TradeStat (imports/exports, HSN-wise) · PIB (government press releases, January 2017 to today, refreshed daily) · RBI (circulars, balance of payments) · MoSPI (CPI/WPI, IIP) · PARIVESH (environmental clearances) · CCIL (bond yields) · BIS (policy rates) · SEBI, NSE/BSE and SEC filings for company data.

Interpretation. Figures carry their vintage and retrieval date; estimates and press-reported numbers are labelled as such; where sources disagree, both are shown. Corrections are made visibly, never silently. Articles are written with AI assistance from the cited sources — AI-generated text can misstate figures even when working from real material, so verify any number that matters to a decision against the linked primary source.

footer

Browse all articles by topic

Every piece on this blog, grouped. Or read the full index.

Agriculture & FertilisersAI ToolsChemicalsClimate & CarbonEnergy & FuelsGas & LNGImport SubstitutionIndustrial PolicyMarkets & FinanceMobility & EVPrices & InflationTextilesTrade & Tariffs

Each topic is a live archive page that updates itself as pieces are labelled. It replaces a hand-kept list that had fallen 18 articles behind.