Thinking global, living local

Biomass Power at Night: The Dispatchable Renewable India's Growth Numbers Left Behind

August 20, 2026

Solar cannot generate a single watt after sunset, which is precisely when India's residential demand — driven overwhelmingly by air conditioners and coolers — can rival or exceed the daytime peak. Biomass power can run at night. It is one of the few renewable sources that actually can. And yet, while India's total renewable capacity (excluding large hydro) grew 178% between December 2019 and July 2026, biomass power grew just 19% — the slowest of any renewable category, in the one slot on the grid where a dispatchable renewable should be winning.

Energy & Fuels · Renewable Grid Economics · 20 August 2026

Biomass Power at Night: The Dispatchable Renewable India's Growth Numbers Left Behind

Skip to article content
Text Size

The pattern in one line: India built a real price signal that should reward power available at night — a mandatory Time-of-Day tariff paying up to 20% less for solar-hour electricity and 10–20% more at peak — but the one renewable source built to answer that signal, biomass, has grown at roughly an eighth the rate of the rest of the renewables mix since 2019.

1. Why solar creates a problem only something else can solve

The "duck curve" is the standard shorthand for what happens to a power grid as solar capacity grows: net demand (total demand minus what renewables supply) sags in the middle of the day as solar output peaks, then ramps up sharply in the evening as the sun sets and demand hasn't. A 2023 CSEP working paper analysing high-resolution 2019 Indian grid data confirms the pattern is already visible here, and warns it will sharpen: "renewable energy's contribution to net demand is lower at periods of high net demand, especially the evening peak," and "storage, or an alternative peaker, would be required to meet the evening peak." The same paper notes that roughly 90% of India's power is still not priced through mechanisms that reflect these real-time grid conditions — a gap the country's Time-of-Day tariff rules, discussed below, are only now starting to close.

The demand side of that evening ramp is increasingly a residential story, not a commercial one. A 2018 Centre for Science and Environment analysis of Delhi's summer electricity demand — cited here for the structural pattern it documents, not as current data — found that late-night demand exceeded afternoon demand on 21 of 31 days in May of that year, driven almost entirely by air conditioner use after commercial establishments had closed; the average day peak (5,280 MW) and average night peak (5,256 MW) were within 0.5% of each other. Whatever the exact numbers look like in 2026, the underlying mechanism — cheap subsidised power plus rising AC ownership plus heat-trapping building design equalling a genuine night-time demand peak — has no obvious reason to have reversed.

2. The price signal now exists, on paper

India's Ministry of Power notified the Electricity (Rights of Consumers) Amendment Rules, 2023 on 14 June 2023 (G.S.R. 437(E)), mandating Time-of-Day (ToD) tariffs nationwide. Under the rule: peak-period tariffs for commercial and industrial consumers with demand over 10 kW must be at least 1.20 times the normal tariff, and at least 1.10 times for other consumers; "solar hours" — an 8-hour daily window specified by each State Commission — must be priced at least 20% below the normal tariff; and peak-hour duration cannot exceed the solar-hours duration. The rule took effect for larger commercial and industrial consumers from 1 April 2024, for other consumers (except agricultural) from 1 April 2025, and immediately upon smart-meter installation for metered consumers.

That last clause matters more than it looks. For the mass of smaller consumers, ToD only bites once a smart meter is actually installed, and India's rollout is still mid-flight: the country has set a goal of installing 250 million smart meters by 2026, and as of a July 2025 industry summary, ToD "adoption is still under consideration by various state regulatory bodies and has not been uniformly implemented across states." A national-level academic literature review on dynamic tariffs for Indian residential consumers, published by researchers at the Council on Energy, Environment and Water in 2024, frames the same rollout as tied directly to the country's renewable-integration math: with India targeting 500 GW of non-fossil capacity by 2030 and variable renewables expected to exceed a 50% share of the generation mix by 2029-30, the "potential supply-demand mismatch" this piece describes as the duck curve is exactly the problem dynamic and time-of-day pricing is meant to solve — but the CEEW review's own emphasis is that DISCOMs "must have a deep understanding of consumer attributes before implementing dynamic tariffs," which is a slower, more deliberate process than a single gazette notification can complete on its own. In practice, the price signal analysed in Section 2 is still reaching only part of the consumer base it was designed for.

Read plainly, this is a tariff structure that pays a real premium — 10 to 20% above normal, and by construction more than 20% above the discounted solar-hour rate — for electricity supplied outside the solar window. Biomass power, unlike solar, can be dispatched into exactly that window. It is, on paper, one of the more direct beneficiaries the ToD rule could have created for a renewable generator.

3. What actually happened to biomass capacity

It didn't show up. The Ministry of New & Renewable Energy's state-wise installed renewable capacity table, dated 31 July 2026, puts India's total bio-power capacity (biomass power/bagasse cogeneration, biomass cogeneration non-bagasse, and waste-to-energy, on-grid and off-grid combined) at 11,747.57 MW — against 164,594.75 MW of solar and 58,136.89 MW of wind. Comparing that to the CSEP paper's December 2019 breakdown (sourced to the Central Electricity Authority), bio-power capacity has grown only 19% in roughly six and a half years, while solar capacity nearly quintupled (+384%) and wind grew 55% over the same window. Excluding large hydro from both years for a fair comparison, India's total non-hydro renewable capacity grew 178% between the two dates — bio-power's growth rate was roughly a ninth of that.

CategoryDec 2019 (MW)Jul 2026 (MW)GrowthShare of non-hydro RE, 2019 → 2026
Solar34,036164,594.75+384%39.5% → 68.7%
Wind37,60858,136.89+55%43.6% → 24.3%
Bio-power9,86111,747.57+19%11.4% → 4.9%
Small hydro4,6775,181.76+11%5.4% → 2.2%
Total (non-hydro RE)86,182239,660.97+178%

2019 figures per CSEP Working Paper 58 (Tongia, Dave & Dalal, 2023), citing CEA's Executive Summary on Power Sector (2019/2020). 2026 figures per Ministry of New & Renewable Energy's state-wise installed capacity table, dated 31 July 2026. Both years exclude large hydro for comparability, since large hydro is tracked and reported separately from the "new RE" category in Indian government statistics.

Growth, Dec 2019 to Jul 2026, by Category Percentage growth in installed capacity, non-hydro renewables +384% Solar +55% Wind +19% Bio-power +11% Small hydro Sources: CSEP Working Paper 58 (2019 figures, citing CEA); MNRE state-wise capacity table, 31 Jul 2026
Solar's growth rate is roughly 20 times bio-power's over the same six-and-a-half-year window.

The result: bio-power's share of India's non-hydro renewable capacity has fallen by more than half, from 11.4% in 2019 to 4.9% in 2026, even as the category it should complement — intermittent solar — came to dominate the mix even more completely, rising from 39.5% to 68.7% of the same total. A grid getting steadily more solar-heavy is, by the CSEP paper's own logic, a grid with a steeper evening ramp and a growing need for exactly the kind of dispatchable renewable supply that isn't scaling.

The state-wise breakdown shows where what little bio-power capacity exists is concentrated: Maharashtra, Uttar Pradesh and Karnataka between them account for roughly 62% of India's total, almost entirely through sugarcane-bagasse cogeneration attached to existing sugar mills rather than purpose-built biomass power plants.

StateBio-Power Total (MW)Share of national bio-power, %
Maharashtra2,999.9725.5
Uttar Pradesh2,329.8919.8
Karnataka1,917.0516.3
Tamil Nadu1,055.129.0
Andhra Pradesh615.025.2
Punjab582.595.0
National total11,747.57100

Per-state Bio-Power Total figures per MNRE's state-wise installed-capacity table as on 31.07.2026, which reports a pre-computed Bio-Power Total column per state (summing bagasse cogeneration, non-bagasse biomass cogeneration, and waste-to-energy on- and off-grid); used here in preference to an earlier attempt at reconstructing state totals from a March 2026 table that dropped zero-value columns inconsistently in extraction.

Bio-Power Capacity by State MW, as on 31 July 2026 — top six states Maharashtra 2,999.97 (25.5%) Uttar Pradesh 2,329.89 (19.8%) Karnataka 1,917.05 (16.3%) Tamil Nadu 1,055.12 (9.0%) Andhra Pradesh 615.02 (5.2%) Punjab 582.59 (5.0%) Source: MNRE state-wise installed renewable-capacity table, as on 31.07.2026
Three states account for roughly 62% of India's total bio-power capacity, almost entirely via sugarcane-bagasse cogeneration.
A tariff rule that pays 10–20% more for power outside the solar window, sitting next to a renewable source that can supply power in exactly that window, and grew at a eighth of the pace of the rest of the renewables mix anyway — the price signal exists; the supply response mostly hasn't shown up yet.
4. What biomass power actually costs to build, and why the ToD premium probably isn't enough

The Central Electricity Regulatory Commission's proposed RE Tariff Order for the third year of the current Control Period (FY2026-27) sets the normative capital cost for a Rankine-cycle biomass power project at ₹638–744 lakh per MW depending on cooling technology and feedstock (rice straw/juliflora-based projects cost more), assumes an 80% plant load factor, and prices in a biomass fuel cost that escalates 3.45% a year from state-specific baseline prices (₹4,262.57 per tonne in Andhra Pradesh and ₹4,852.24 per tonne in Haryana, for example). Run through CERC's levellised-tariff methodology, the resulting applicable tariff for a standard water-cooled, travelling-grate-boiler biomass plant comes out to roughly ₹9.6–11.1 per kWh across the major biomass states — split into a levellised fixed-cost component of about ₹3.4–3.5/kWh and a variable fuel-cost component of ₹6.3–7.6/kWh that dominates the bill.

That figure is the real explanation the ToD story alone doesn't supply. A 10–20% peak-hour premium is a percentage of the "normal tariff" a state commission sets — for competitively bid solar and wind power in India, that normal tariff typically sits in the ₹2.5–3.5/kWh range, several times lower than biomass's own levellised cost before any ToD premium is even applied. A 2018 study on biomass pellet-based power generation in India, published by CEEW-affiliated researchers, reached an independent version of the same conclusion from a different angle: the levelised cost of biomass-pellet electricity was estimated at €0.12 per kWh, "even higher than the cost of imported coal-based electricity," with viability hinging on feedstock surplus, transport distance from farm to plant, and cooling technology — the same variables CERC's cost norms are built around. Two structurally different pricing exercises, run seven years apart, arrive at the same basic verdict: biomass power in India is expensive to generate on its own economics, well before anyone gets to ask whether a night-time tariff premium can close the gap.

5. What this piece can't fully explain

Biomass power's slow growth almost certainly has causes this piece's sourcing doesn't cover in depth — feedstock logistics and year-round agricultural-residue supply chains beyond the state-level fuel-price table above, existing power purchase agreement structures that may not yet reflect ToD pricing at the generator level, and the practical lag between a 2023-24 tariff rule taking effect and a biomass plant being financed, built and commissioned. One structural cause is now clearer, though: the ToD price signal itself is still incompletely deployed, gated behind a 250-million-smart-meter rollout target for 2026 and uneven state-by-state regulatory implementation, so a meaningful share of the consumer base a biomass generator might sell peak-hour power to isn't actually paying ToD rates yet. What this piece does establish is that the cost gap is large enough that the ToD premium looks unlikely to be the deciding factor on its own: a plant charging ₹9.6–11.1/kWh needs a buyer willing to pay that rate, ToD premium or not, and this piece's sourcing doesn't cover who is actually signing power purchase agreements at CERC's normative biomass tariff versus how much biomass capacity is being built by sugar mills for captive/bagasse-cogeneration use, which follows different economics entirely.

What this piece does not establish. The 2018 CSE Delhi demand analysis is cited only to illustrate a structural mechanism (AC-driven night demand rivalling day demand); its specific MW figures are eight years old and should not be read as current 2026 conditions, for Delhi or nationally. Whether biomass generators are actually receiving ToD-linked pricing in practice (as opposed to legacy power purchase agreements predating the 2023 rule) was not established in this piece's sourcing. The CSEP paper's grid-balancing analysis is based on 2019 data; more recent equivalent studies may exist but were not part of this piece's source set.
Documents & sources · Grid-balancing theory, the duck-curve mechanism, and the "storage or an alternative peaker" finding per Tongia, R., Dave, A., with Dalal, U. (2023), "Understanding Time-of-Day and Seasonal Variations in Supply and Demand for Electricity in India: 2019 Analysis Using High Temporal Resolution Data," CSEP Working Paper 58, Centre for Social and Economic Progress, October 2023, citing CEA's Executive Summary on Power Sector (2019, 2020b) for the December 2019 capacity breakdown. Time-of-Day tariff mechanics per the Ministry of Power's Electricity (Rights of Consumers) Amendment Rules, 2023, Gazette of India notification G.S.R. 437(E), dated 14 June 2023. Smart-meter rollout target (250 million by 2026) and uneven state-level ToD implementation per Enphase Energy's "All You Need to Know About Time of Day (ToD) Tariffs in India," 20 July 2025, citing Prayas Energy Group. Dynamic-tariff implementation challenges and India's 500 GW non-fossil/50%+ variable-renewable-share 2030 context per Aggarwal, D., Malhotra, M., and Agrawal, S. (2024), "Implementing Dynamic Tariffs for Residential Consumers: A Literature Review," Proceedings of Energise 2023, Alliance for an Energy Efficient Economy, authored by researchers at the Council on Energy, Environment and Water (CEEW). State-wise renewable capacity, both national totals and the per-state Bio-Power Total breakdown, per Ministry of New & Renewable Energy's published capacity table dated 31 July 2026 (mnre.gov.in/en/physical-progress). Biomass power's normative capital cost, plant load factor, fuel cost and levellised tariff figures per the Central Electricity Regulatory Commission's proposed RE Tariff Order for the third year of the Control Period, FY2026-27 (cercind.gov.in). Biomass pellet power economics and the €0.12/kWh levelised-cost estimate per Purohit, P. and Chaturvedi, A. (2018), "Biomass Pellets for Power Generation in India: A Techno-Economic Evaluation," published via the Council on Energy, Environment and Water (CEEW). Delhi 2018 night-vs-day demand pattern per Centre for Science and Environment's "Power Pangs" press release, 12 June 2018, cited here for illustrative/structural purposes only and explicitly not as current data. Nothing here is investment advice; project-level biomass generation economics vary by feedstock, state and power purchase agreement and should be verified independently before any capital decision.

About this article: Researched, written and edited by Umashankar Triplicane Dwarakanathan, with AI research assistance; every figure is meant to trace to the primary source cited. See the Editorial Policy for how sourcing, AI use and corrections work.

Rows of photovoltaic panels at a solar installation in India
Solar is where much of India's new generation capacity is going. Solar panels in India.jpg, User: Manjunatha G, WELL Labs, CC BY-SA 4.0, via Wikimedia Commons.
Umashankar Triplicane Dwarakanathan
Contact Us
Umashankar Triplicane Dwarakanathan
Investment Promotion & Energy-Sector Leader · Chennai, Tamil Nadu, India
LinkedIn → GitHub → Email +91 78273 81696
How this site works

Data-led analysis of India's trade, currency and industrial policy. Every article is built from primary official sources, and every figure links back to the release, table or filing it came from.

Sources. DGCI&S TradeStat (imports/exports, HSN-wise) · PIB (government press releases, January 2017 to today, refreshed daily) · RBI (circulars, balance of payments) · MoSPI (CPI/WPI, IIP) · PARIVESH (environmental clearances) · CCIL (bond yields) · BIS (policy rates) · SEBI, NSE/BSE and SEC filings for company data.

Interpretation. Figures carry their vintage and retrieval date; estimates and press-reported numbers are labelled as such; where sources disagree, both are shown. Corrections are made visibly, never silently. Articles are written with AI assistance from the cited sources — AI-generated text can misstate figures even when working from real material, so verify any number that matters to a decision against the linked primary source.

footer

Browse all articles by topic

Every piece on this blog, grouped. Or read the full index.

Agriculture & FertilisersAI ToolsChemicalsClimate & CarbonEnergy & FuelsGas & LNGImport SubstitutionIndustrial PolicyMarkets & FinanceMobility & EVPrices & InflationTextilesTrade & Tariffs

Each topic is a live archive page that updates itself as pieces are labelled. It replaces a hand-kept list that had fallen 18 articles behind.