An amendment to the Oilfields (Regulation and Development) Act, in force since April 2025, expanded the Centre's power to let solar and wind projects sit on the same land as an oil or gas lease. It's the reason India's biggest oilfield operator, ONGC, now has a green subsidiary. Sixteen months on, that subsidiary's own rooftop solar — the renewable capacity actually sitting on ONGC's own petroleum-lease land — adds up to under a megawatt. Its 4-gigawatt renewable portfolio came from buying somebody else's company instead.
India Let Oil Companies Put Solar on Their Own Leases. A Year On, ONGC's Own Build Is Under 1 Megawatt — It Bought 4 Gigawatts Instead.
What ORDA 2025 actually changed
The Oilfields (Regulation and Development) Amendment Act, 2025 received the President's assent on 28 March 2025 and came into force on 15 April 2025, amending the parent Oilfields (Regulation and Development) Act, 1948. Most of the amendment is about the petroleum business itself — it replaces the old "mining lease" terminology with a single "petroleum lease" covering exploration, development and production together, extends lease tenure to up to 30 years (extendable for a field's full economic life), and adds a new Section 13A grandfathering leases granted before the amendment under their original terms.
The renewable-energy hook that this piece is actually about sits somewhere less dramatic: the amendment expanded the list of things the Central Government may make rules about under the Act to explicitly include "comprehensive energy projects" at oilfields — the planning, development, installation, sharing and use of infrastructure for both petroleum operations and solar, wind and other renewable energy projects on the same licensed land, alongside decarbonisation, carbon capture and storage (CCUS), hydrogen and coal gasification. It is not a standalone "you may now build solar here" clause; it is a rule-making power, and the Centre exercised it through a companion notification, the Petroleum and Natural Gas Rules, 2025. That rulebook's Chapter VII — "Environment Protection, Decarbonisation, Monitoring of Greenhouse Gas Emissions and Flared Gas" — is where the actual obligations and permissions sit: GHG monitoring and reporting requirements, a CCS/CCUS framework, and site-restoration funds with five years of mandatory post-closure monitoring, alongside the provision letting a lease-holder co-locate renewable generation on the same acreage. For CO₂ storage specifically, the mechanics of where that gas would actually go are territory this blog has already mapped, well basin by well basin.
What can be verified about ONGC's land is more modest but still real: under the nomination regime, DGH and the petroleum ministry's own block-award data put ONGC's licensed acreage at roughly 94,358 sq km (9 petroleum exploration licences and 334 petroleum mining leases); ONGC's own FY23 disclosures separately describe it as holding India's largest exploratory acreage, at 162,701 sq km as of 31 March 2023, a figure that includes NELP- and OALP-awarded blocks alongside nomination acreage. Both numbers describe genuinely large, already-licensed, already-grid-connected land — the kind ORDA 2025's rule-making power was written for. Neither number, on its own, tells you how much of it is actually suitable for solar or wind at scale; that would need a site-by-site resource and land-use survey this piece did not find published anywhere.
The number ONGC's own land has produced so far
ONGC's dedicated renewable-energy arm, ONGC Green Limited, was approved for formation by the petroleum ministry on 5 December 2023 and incorporated on 27 February 2024 — after ORDA 2025's predecessor bill was already moving through Parliament, and well before the amendment itself took effect. Its mandate is exactly what the new rule-making power was meant to enable: renewable generation, green hydrogen and decarbonisation projects, including on ONGC's own oilfield acreage.
Measured against that mandate, the organic build on ONGC's own land is, so far, negligible. ONGC's rooftop solar — the renewable capacity that is actually sitting on land the company already holds and controls — consists of 11 grid-connected installations totalling 647 kilowatts and 6 off-grid installations totalling 49 kilowatts, a combined 696 kW. That is a rounding error against any of the gigawatt-scale numbers this piece discusses next, and it is not obviously accelerating: no utility-scale ground-mounted solar or wind project sited on ONGC's own petroleum-lease acreage under the new legal framework was found publicly announced as of this piece's research. ORDA 2025 removed the legal obstacle to building on the land ONGC already has; sixteen months on, that removal has not yet translated into ONGC's own construction crews breaking ground on it.
How ONGC actually got to gigawatt scale: it didn't build, it bought
The renewable capacity ONGC can actually point to came from an acquisition, not a Development Plan filed under the new rules. In February 2025, ONGC NTPC Green Private Limited (ONGPL) — a 50:50 joint venture between ONGC Green and NTPC Green Energy Limited — signed a share purchase agreement for Ayana Renewable Power at a headline enterprise value of ₹19,500 crore. That figure, widely reported at signing and on CCI clearance, is the deal's enterprise value — equity plus the debt ONGPL assumed as part of the transaction — not the cash paid for the shares themselves. The actual equity consideration, paid on completion on 27 March 2025, was ₹6,248.5 crore (₹23.22 per share); the roughly ₹13,250 crore gap between the two figures is Ayana's assumed debt. ONGC funded its half of the equity purchase through a ₹3,300 crore rights issue into ONGC Green, with NTPC Green matching ₹3,124.25 crore for its half.
Ayana itself brought a portfolio of roughly 4.1 GW of operational and under-construction/development solar and wind assets — built by Ayana over the preceding several years, largely on land Ayana itself had assembled, not ONGC's petroleum leases. With Ayana folded in, ONGC and ONGC Green's combined renewable portfolio stood at 2.85 GW as of November 2025, with further tenders in progress (300 MW of wind, 600 MW of solar, 1,200 MWh of battery storage) that would take the total to roughly 3.70 GW, against a stated company target of 10 GW by 2030. Every gigawatt of that build to date sits on land Ayana already controlled before ONGC bought it — not on the petroleum-lease acreage ORDA 2025 specifically unlocked.
The one-line version. The law that was supposed to let an oil company put solar on its own oilfields has, so far, produced a company that bought somebody else's already-built solar and wind portfolio instead. That may still be a rational business decision — M&A is faster than a Development Plan filing — but it is not evidence that oilfield land itself is being converted, which was the premise the law was written to enable.
Why land alone was never going to be the whole story
None of this means ORDA 2025 was pointless, or that oilfield land won't eventually matter. India's own demand math is why the option exists at all: the Central Electricity Authority's Long-Term National Resource Adequacy Plan (LT-NRAP), published in March 2026, projects electricity demand climbing from roughly 1,846 billion units in FY2025-26 to 3,365 billion units by FY2035-36 — a trajectory that, in the CEA's own optimal generation mix for that year, needs 509 GW of solar and 155 GW of wind installed, against just 150.26 GW of solar and 56.09 GW of wind actually installed as of March 2026 (part of 283.46 GW of total non-fossil capacity, per the renewable energy ministry's own physical-progress data). Closing that gap needs land, and land that is already licensed, already has grid connections and existing environmental clearances, and doesn't require a fresh site-acquisition fight is exactly the kind of asset a law like ORDA 2025 is written to unlock, whatever ONGC has or hasn't done with it yet.
What ONGC's own numbers suggest is that having the legal right to build isn't the binding constraint. Three more concrete ones are:
- Transmission. The Green Energy Corridor programme's next phase, GEC Phase 3, was proposed in the FY26 Budget at an estimated cost of roughly ₹56,000 crore (the Centre covering about 40%, the rest from state governments and other stakeholders), meant to build the HVDC transmission backbone — concentrated in Gujarat and Rajasthan — that GEC Phases 3 and 4 together are meant to let roughly 150 GW of renewable power actually reach the grid. It isn't due to commission until around 2029-30. Without it, any large new solar or wind build in Gujarat specifically — ONGC's oilfield land included — risks being curtailed for lack of somewhere to send the power, the same evacuation bottleneck this blog has already documented for India's wind fleet more broadly.
- Institutional mismatch. ONGC was constituted to find and produce petroleum; its roughly 32,000-strong workforce is trained for that, not for developing and operating renewable generation. ONGC Green exists precisely to bridge that gap, but a subsidiary formed in February 2024 competing for the parent company's capital allocation against oilfield exploration and enhanced-oil-recovery projects is a genuinely different institutional problem than simply having a legal green light.
- Offtake risk in deficit states. Any large-scale RE project ultimately needs a buyer willing and able to pay for the power over 20-25 years, and India's most power-deficient states — the ones with the most room for new demand — also tend to run the DISCOMs with the weakest balance sheets and the histories of payment delay this blog's own DISCOM debt-relief piece has covered. A long-term power-purchase agreement without a central or state payment backstop is a real, not theoretical, risk to any large new RE asset, ONGC's or anyone else's.
What would fix this
- DGH and the petroleum ministry should require ONGC to file at least one Development Plan for renewable generation on its own oilfield acreage, with a public site and timeline. ORDA 2025 created the legal pathway; nothing currently forces ONGC to actually use it rather than substitute an acquisition for it.
- ONGC Green's annual disclosures should separately report organically developed capacity against acquired capacity. A single "2.85 GW, heading to 10 GW" headline currently lets an M&A deal and a from-scratch oilfield-solar project read identically, when they represent completely different progress against the law's actual purpose.
- The Ministry of Power should prioritise GEC Phase 3's Gujarat and Rajasthan legs specifically, since that is where both ONGC's largest acreage and its Ayana-derived generation cluster already sit; a 2029-30 commissioning date leaves a multi-year window in which any oilfield-sited solar would have nowhere to send surplus power.
- Any future oilfield-sited RE project selling into a deficit state should carry a tripartite Centre-state payment backstop as standard, on the model already used for NTPC's supply into states like Bihar and Uttar Pradesh, rather than leaving each project to negotiate its own offtake security from scratch.
These are proposals from this blog, not recommendations any agency has adopted.
Sources and caveats
ORDA 2025's assent date (28 March 2025), commencement (15 April 2025), lease-terminology and tenure changes, Section 13A grandfathering, and the expanded rule-making power covering "comprehensive energy projects" (renewables, decarbonisation, CCUS, hydrogen, coal gasification at oilfields) are from the Gazette of India notification of Act No. 6 of 2025 (egazette.gov.in; CG-DL-E-28032025-262080) and DGH's own copy of the amended Act, cross-checked against Chambers and Partners' and TeamLease RegTech's legal summaries of the amendment. The Petroleum and Natural Gas Rules, 2025 (G.S.R. 888(E), 9 December 2025, Gazette of India Extraordinary CG-DL-E-11122025-268409) and its Chapter VII on environment protection, decarbonisation, GHG monitoring and site-restoration funds were read in the Gazette’s own text on 28 October 2026, through the SansadSaar index of the archive.org Gazette of India collection; earlier versions of this piece relied on current-affairs and legal-explainer coverage (Insights on India, C4S Courses) and called it Chapter VIII. ONGC's nomination-regime acreage (~94,358 sq km, 9 PEL + 334 PML blocks) is from the petroleum ministry's own block-award data (mopng.gov.in); the 162,701 sq km exploratory-acreage figure as of 31 March 2023 is ONGC's own stated figure as reported in contemporaneous business-press coverage (Business Standard) of its exploration activity, not independently verified against ONGC's full annual report. ONGC Green Limited's formation approval (5 December 2023) and incorporation (27 February 2024) are from Business Standard's and Energy Asia's coverage of the incorporation filing. ONGC's rooftop solar figures (11 grid-connected plants/647 kW, 6 off-grid plants/49 kW) and the 2.85 GW combined ONGC/ONGC Green renewable portfolio as of November 2025 (with 300 MW wind, 600 MW solar and 1,200 MWh BESS tenders in progress toward ~3.70 GW, against a 10 GW-by-2030 target) are from Power Line's and Renewable Watch's October-2025 coverage of ONGC's renewable strategy. The Ayana Renewable Power acquisition — the ONGPL 50:50 joint-venture structure, the ₹19,500 crore enterprise-value SPA, CCI clearance, the 27 March 2025 completion date, the ₹6,248.5 crore (₹23.22/share) actual equity consideration, and the ₹3,300 crore/₹3,124.25 crore rights-issue funding split — is from Business Standard's, India Infoline's and Energetica India's reporting on the deal's signing, CCI clearance and completion, and ONGC's own announcement of the SPA; the ~4.1 GW Ayana portfolio figure is Ayana's own stated figure via its corporate website, without an independently sourced solar/wind split. The CEA's Long-Term National Resource Adequacy Plan (LT-NRAP, March 2026) and its FY2035-36 targets (509 GW solar, 155 GW wind, 3,365 BU total demand, 1,121 GW total installed capacity) are corroborated across Energetica India's, Renewable Watch's and Mercom India's coverage of the plan's release; the FY2025-26 base-year demand figure of roughly 1,846 BU is consistent with CEA's separately published National Electricity Plan trajectory but was not independently pinned to a verbatim quotation from the LT-NRAP's own tables, and should be read as approximate. India's non-fossil installed capacity as of 31 March 2026 (283.46 GW; solar 150.26 GW, wind 56.09 GW; 55.3 GW added in FY2025-26) is from the Ministry of New and Renewable Energy's own physical-progress data as announced via PIB (PRID 2250039). Green Energy Corridor Phase 3's estimated cost (~₹56,000 crore), funding split, HVDC-backbone description and ~2029-30 target commissioning are from Down To Earth's and Saur Energy's coverage of the Union Budget FY26 announcement. The claim, found in an earlier private strategy document this piece's author had access to, that ONGC controls 5.66 lakh sq km of petroleum acreage and that Adani's Khavda Renewable Energy Park sits on ONGC petroleum-lease land, was independently checked and found unverifiable (the acreage figure) and false (the Khavda-land claim, which is Gujarat government wasteland under a separate allotment policy) respectively; neither claim, nor any GW-potential figure derived from them, appears anywhere in this piece. Nothing in this piece is investment advice. Compiled via web research on 28 September 2026.
About this article: Researched, written and edited by Umashankar Triplicane Dwarakanathan, with AI research assistance; every figure is meant to trace to the primary source cited. See the Editorial Policy for how sourcing, AI use and corrections work.