A Hectare Under a Power Line Now Pays Three to Six Times What One Over a Pipeline Does

October 26, 2026

The Ministry of Power’s 6 October 2026 guidelines pay 30–60% of market value for the land under a transmission corridor and 200% for tower bases; the 1962 pipeline law pays 10%.

Energy · Transmission · Land compensation

A Hectare Under a Power Line Now Pays Three to Six Times What One Over a Pipeline Does

Skip to article content
Text Size

Revised · v1.0.0

30% / 45% / 60%Corridor payment as a share of market value: rural / municipalities and other urban planning areas / corporations and metros
200%Tower-base land, as a share of market value
10%What a gas or oil pipeline owes for the land it uses, as a share of market value (1962 Act, s.10(4))
3 valuersOutliers clipped to ±20% of the median before averaging

On 6 October 2026 the Ministry of Power told every state that the land under and around a high-voltage line is worth 30% to 60% of its market value as compensation, and the land under each tower twice its market value. The law that lets a pipeline cross the same field pays 10% of market value, once, on top of any damage to crops and trees.

For one hectare, a power line therefore pays three to six times what a pipeline does. The gap is not new in percentage terms for rural land: the ministry's June 2024 letter already said 30% and 200%. What the new letter changes is how the market value is found, who can challenge it, and who ultimately pays.

Scope. The 2026 letter is a set of guidelines under Sections 67 and 68 of the Electricity Act, 2003 and the Indian Telegraph Act, 1885, not a statute. It applies to inter-state transmission (ISTS) lines at 66 kV and above, and only where a landowner objects that the circle rate is below the market rate. Pipeline compensation, by contrast, is written into an Act of Parliament. The comparison below is between a guideline and a statute, and between two different physical footprints, so read the worked example as arithmetic on a hectare, not as a claim that each landowner is paid these sums.

What the 6 October 2026 letter says

The letter (F.No. 3/4/2016-Trans-Part(4)), signed by an Under Secretary and issued with the Minister's approval, is addressed to the Chief Secretaries of all states and union territories, the CEA, CERC, Grid India, CTUIL and all transmission licensees. It states its own reason: many states have yet to specify how market rate is to be found, and landowners complain that compensation is still being proposed at circle rates "significantly lower than market rates". Its main rules:

  • Base rule. Compensation is ordinarily on the circle rate, guideline value or stamp-duty rate, unless the market rate is higher, in which case the land value is the market rate fixed by a Market Rate Committee (MRC) chaired by the District Magistrate or Collector.
  • Three valuers. Three valuers per district are picked by the district administration from the list empanelled by the Insolvency and Bankruptcy Board of India, paid by the transmission service provider (TSP). Each values along the alignment, plus one village into the next district, and files a sealed report within 21 days. The three reports are opened together.
  • Clipping. The highest and lowest valuations are brought within ±20% of the median. The market rate is the average of the three after that adjustment.
  • Tower base. 200% of market value, for the area inside the four legs at ground level plus one metre on each side.
  • Corridor. Land inside the right-of-way corridor, as defined in Schedule VII of the CEA technical regulations (Annex I of the letter, the CEA's 9 October 2025 amendment), gets 30% of market value in rural areas, 45% in municipalities, nagar panchayats and other notified urban planning areas, and 60% in municipal corporations and notified metropolitan areas. No construction of any kind is allowed in the corridor. The letter adds that states may decide the rate "depending on the area and urgency of the work".
  • Payment and appeal. One-time and upfront, by digital means where possible. An aggrieved party can appeal to a state-notified Appellate Authority within 30 days of the MRC's notified rate, but the appeal is admitted only if the appellant agrees to let work start on site while it is decided. The authority's decision is final.
  • Who pays. If the TSP's actual compensation differs from the RoW cost assumed when the line was bid, the difference can be passed through under "Change in Law" by CERC.

The letter is a scan; I checked the page images for the figures used here (the 200%, the three corridor percentages and the two illustrations). The ministry's own illustration with valuations of ₹40, 70 and 110 lakh clips the first to 56 and the third to 84, giving a market value of ₹70 lakh. A second, with ₹45, 50 and 150 lakh, clips the last to 60 and gives ₹51.67 lakh. The clipping matters most when one valuer is far off: it limits how far a single low or high report can move the average, but the average still sits between 80% and 120% of the median.

What changed from June 2024

The 14 June 2024 letter is on the ministry's site. Set against it, the 2026 letter keeps the circle-rate base, the 200% tower-base rate and the one-metre margin, and it changes the following.

Item14 June 2024 letter6 October 2026 letter
Who fixes market valueDistrict Magistrate / Collector, in the manner the state specifiesMarket Rate Committee, from three independent valuers' reports
Corridor payment (% of land value)30, flat; states may set a higher rate; corridor width per CEA 2022 regulations30 rural, 45 smaller urban areas, 60 corporations and metros; corridor width per CEA 2025 amendment
Tower base (% of land value)200200
AppealNone stated30 days, to a state Appellate Authority; work proceeds meanwhile
Cost recoveryNot statedPass-through under Change in Law by CERC
StatusStates may adopt or issue their own; central guideline applies in defaultSame, and applies to ISTS where owners object that circle rates are below market
Two earlier letters not found. The 2026 letter says it supersedes letters of 14.06.2024, 21.03.2025 and 15.12.2025. I could find and read only the first. The ministry's document index shows no 21 March 2025 or 15 December 2025 letter on RoW, and a web search for those dates found nothing. Whatever those two changed is not in this comparison.

What a pipeline pays

This blog's earlier piece on Right of User notifications mapped how a pipeline gets onto land. The compensation side is in Section 10 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962, in an unofficial copy of the Act that shows amendments to 2012; the 10% rule in Section 10(4) is also stated in a Lok Sabha answer. Three rules matter:

  • Section 10(1) and (3): compensation for actual damage, loss or injury, such as removed crops and trees or temporary severance of the land, fixed by the competent authority, with the District Judge as the forum if either side disagrees.
  • Section 10(4): on top of that, "compensation calculated at ten per cent. of the market value of that land on the date of the notification" under Section 3(1), to the owner and anyone whose enjoyment of the land is affected.
  • Sections 9 and 7: the owner may keep using the land as before, but may not build, dig a tank or well, or plant trees on it; the pipeline must lie at least one metre deep and not under homes or land with permanent structures.

The 1997 rules add that the competent authority may take the prevailing land rate from the registration authority, any land acquisition authority, or the officer who fixes reserve price, and the rate used must not be below that reserve price (1997 rules). The Act sets no multi-valuer procedure and no tower-like premium. I found no amendment to Section 10 in the copy I read; its footnotes record only Act 13 of 1977 and Act 9 of 2012, and the 2012 Act replaced Sections 15 and 16, the penalty provisions. Whether a 2026 law touched this Act is something I could not check (see below).

One hectare, three ways

All figures here are illustrative. I use ₹70 lakh per hectare as the market value, which is the market value the ministry's own Illustration 1 arrives at, and ₹40 lakh per hectare as a hypothetical circle rate. Real values vary enormously by district.

CaseRate (% of land value)At market ₹70 lakh/ha (₹ lakh)At circle ₹40 lakh/ha (₹ lakh)
Pipeline, land in the right-of-user strip (s.10(4))107.004.00
Power line corridor, rural3021.0012.00
Power line corridor, municipality or other urban planning area4531.5018.00
Power line corridor, corporation or metro6042.0024.00
Land under a tower base200140.0080.00

The pipeline row assumes the competent authority uses market value, as Section 10(4) requires, and excludes any separate damage payment for crops or trees. The circle-rate column for the pipeline is only for comparison. For the power line, the guideline pays on circle rate unless the MRC finds a higher market rate, so in practice the second column is what applies where no objection and no valuation happens.

A kilometre of 400 kV line

The CEA's Schedule VII table (Annex I, Table 1) gives the corridor width for a 400 kV double-circuit line with Moose conductor on normal route as 46 m, at a design span of 400 m. A kilometre of such line therefore has a corridor of 46 m × 1,000 m = 4.6 hectares, and about 2.5 towers at a 400 m span. I assume, purely for illustration, a tower footprint of 12 m square between legs, which with the one-metre margin on each side becomes 14 m × 14 m = 196 m² per tower, or 490 m² for 2.5 towers (0.049 ha). The 12 m figure is my assumption, not from the letter.

ComponentWorkingAt market (₹ lakh)At circle (₹ lakh)
Corridor, rural, 4.6 ha4.6 × 30% × land value96.6055.20
Tower bases, 0.049 ha0.049 × 200% × land value6.863.92
Total per kmSum103.4659.12

The market-rate rule adds ₹44.34 lakh per kilometre in this example, 75% more than the circle-rate figure. On a project with hundreds of kilometres that is a bid-cost item, which is why the CERC pass-through clause matters: a developer who bid on one assumption and has to pay another can recover the difference through tariffs, and tariffs are paid by consumers. The letter does not say whether the tower-base area is also counted inside the corridor area. In this example it is counted twice (0.049 ha is 1% of 4.6 ha).

Why the pipeline gap matters. The two regimes pay for different things. A pipeline sits at least a metre underground and the owner may keep ploughing; a tower occupies the surface and the corridor bars construction. Both bar buildings, but the pipeline strip's width is not in the Act or the rules I read, so I cannot say how its area compares with a 46 m corridor. What can be compared is the unit rate on the land that is affected, and that differs by a factor of three or more.

Will states follow?

The letter does not command them. It says states "may adopt these guidelines in their entirety or issue their own modified policy", and the central guidelines apply where a state has yet to specify how land value is determined. The 2024 letter had the same structure. States that already have their own rules therefore keep them, and the appellate authority and the MRC must still be set up by each state. The ministry's index shows the 2026 letter itself but I did not find any state notification adopting it.

For readers following the transmission build-out, this is one more cost and delay variable. The blog's piece on Green Energy Corridor III noted that right-of-way disputes were among the reasons the first two phases ran late; the 2026 letter is the centre's attempt to settle those disputes with a faster price-finding process (valuers report in 21 days) and a quick appeal that does not stop work.

What I could not check

  • The 21 March 2025 and 15 December 2025 letters: not found.
  • Whether any 2026 law changed the 1962 Act's compensation. India Code lists a Jan Vishwas (Amendment of Provisions) Act, 2026 among amending acts according to a search summary; I did not open its text and did not confirm what it did to this Act.
  • The width of a pipeline right-of-user strip, and so a like-for-like comparison per kilometre.
  • Whether any state has adopted the 2026 letter.

Sources: Ministry of Power, Guidelines for payment of compensation in regard to Right of Way (RoW) for transmission lines, F.No. 3/4/2016-Trans-Part(4), 6 October 2026, with Annex I (CEA Amendment Regulations, 2025, Gazette 10 October 2025), Annex II (cost matrix) and Annex III (SOP); Ministry of Power, letter of 14 June 2024; Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (unofficial copy with amendments to 2012); Lok Sabha, answer stating the Section 10(4) ten-per-cent rule; Ministry of Petroleum and Natural Gas, Amendment Rules, 1997. The worked examples are illustrative arithmetic on assumed land values and an assumed tower footprint, not observed payments. Earlier posts: Right of User; Green Energy Corridor III.

About this article: Researched, written and edited by Umashankar Triplicane Dwarakanathan, with AI research assistance; every figure is meant to trace to the primary source cited. See the Editorial Policy for how sourcing, AI use and corrections work.

Umashankar Triplicane Dwarakanathan
Contact Us
Umashankar Triplicane Dwarakanathan
Investment Promotion & Energy-Sector Leader · Chennai, Tamil Nadu, India
LinkedIn → GitHub → Email +91 78273 81696
How this site works

Data-led analysis of India's trade, currency and industrial policy. Every article is built from primary official sources, and every figure links back to the release, table or filing it came from.

Sources. DGCI&S TradeStat (imports/exports, HSN-wise) · PIB (government press releases, January 2017 to today, refreshed daily) · RBI (circulars, balance of payments) · MoSPI (CPI/WPI, IIP) · PARIVESH (environmental clearances) · CCIL (bond yields) · BIS (policy rates) · SEBI, NSE/BSE and SEC filings for company data.

Interpretation. Figures carry their vintage and retrieval date; estimates and press-reported numbers are labelled as such; where sources disagree, both are shown. Corrections are made visibly, never silently. Articles are written with AI assistance from the cited sources — AI-generated text can misstate figures even when working from real material, so verify any number that matters to a decision against the linked primary source.

footer

Browse all articles by topic

Every piece on this blog, grouped. Or read the full index.

Agriculture & FertilisersAI ToolsChemicalsClimate & CarbonEnergy & FuelsGas & LNGImport SubstitutionIndustrial PolicyMarkets & FinanceMobility & EVPrices & InflationTextilesTrade & Tariffs

Each topic is a live archive page that updates itself as pieces are labelled. It replaces a hand-kept list that had fallen 18 articles behind.